Here, the developers were in Cambridge, MA, the product owners were in San Francisco, the testers were in Bangalore, and the project manager was always flying somewhere, because the project manager was shared among several projects. The developers knew about timeboxed iterations, so they used timeboxes. Senior management had made the decision to fire all the local testers and buy cheaper tester time over the developers’ objections and move the testing to Bangalore. The Indian testers were very smart, and unfamiliar with the product, so the developers suggested the testers test feature by feature inside the iteration.